🏗️ Part of: Building & Developer Costs →
Faheema Sheikh · SA Property & Investment Analyst · 15 Years Experience
๐Ÿ• Last Updated: September 2026  ยท  Rhino Slabs Spec & SA Rib and Block Pricing

Quick answer: A rib and block slab uses pre-stressed concrete ribs at 590mm centres, hollow infill blocks between them, and a 50mm concrete topping (Rhino Slabs' published spec). Block heights run S120 to S290, giving slab depths of 170mm to 340mm. Supply-only material cost is roughly R140–R510/m² plus topping, based on 2023/24 pricing not yet re-confirmed for 2026, always get a current quote.

๐Ÿ—๏ธRib and Block Calculator: Enter Slab Details
Direction the ribs span, max 7.8m per rib (Rhino Slabs spec)
Direction across the ribs
๐Ÿ—๏ธ Total Blocks Required
โ€”
โ€”
โ€”
Ribs Required
โ€”
Total Rib Length
โ€”
Topping Concrete
โ€”
Finished Slab Depth
โ€”
Est. Supply Cost (2023/24 pricing)
โ€”
Floor Area

โš ๏ธ For planning purposes only. Slab depth, span and reinforcement must be confirmed by a structural engineer before ordering.

How to Use This Calculator

Enter your slab's length (the direction the ribs span) and width (the direction across the ribs), both in metres.

Choose your block type from S120 to S290, based on the slab depth your structural engineer has specified. Results show ribs, blocks, topping concrete volume and an estimated supply cost.

What a rib and block slab actually is

A rib and block slab is a suspended-floor system built from pre-stressed concrete ribs laid across a span, with hollow concrete infill blocks placed between them, then finished with a thin reinforced concrete topping. It's used for basement, first-floor and roof slabs as an alternative to a fully poured concrete slab, and needs no cranes or formwork to install, the props go in, the ribs and blocks are packed by hand, and levelling happens as the weight settles onto the props.

The figures on this page are Rhino Slabs' own published specification, not a nationwide South African standard. Other SA precast suppliers (Royal Concrete Slabs, Amalgamated Slab Company, Mobicast) use different block series and dimensions for the same product category, always confirm the exact spec with your chosen supplier before ordering.

Rhino Slabs block types and dimensions

Block TypeBlock HeightDimensions (L×W×H)Finished Slab Depth
S120120mm450×220×120mm170mm
S150150mm450×220×150mm200mm
S205205mm450×220×205mm255mm
S290290mm450×220×290mm340mm

Ribs are pre-stressed, 140mm × 60mm in cross-section, weigh 17kg per metre, and are rated to span up to 7.8m. Rib centres are fixed at 590mm regardless of block type, and the concrete topping is consistently 50mm across all four block heights (each slab depth is exactly the block height plus 50mm).

Rib and block span limits

There is no published span-per-block-type lookup table, slab depth and span are determined by a structural engineer per SANS 1879 and SANS 10100 based on your building's actual load and layout, not a fixed rule this calculator can give you. As general context only: Rhino Slabs' own ribs are rated to span up to 7.8m, and rib and block systems as a category generally achieve clear spans up to around 10m. Always get an engineer's design before ordering, this calculator estimates quantities for a design you already have, it does not replace one.

Rib and block cost per m² in South Africa

Based on the most detailed published breakdown found, dated 2023/24 and not yet re-verified for 2026, supply-only material for ribs and blocks runs roughly R140–R510/m² depending on block depth, plus around R210/m² for topping concrete if you're managing that yourself. A fully supplied and installed slab runs approximately R825–R1,080/m². Treat this as a starting guideline, not a current market rate, and get a fresh quote from your supplier before budgeting, building material pricing moves and this specific figure is the oldest sourced on this page. If you're pricing a full build rather than just the slab, our Building Cost Calculator covers the wider construction budget this fits into.

A worked example: 6m × 4m slab, S150 blocks

Take a 6m × 4m floor (24m²) using S150 blocks (200mm slab depth). Ribs run the 6m length and are spaced at 590mm across the 4m width, needing 8 ribs (CEIL(4 ÷ 0.59) + 1), each 6m long, for 48m of total rib length. Between the 8 ribs sit 7 bays, each needing blocks laid end to end along the 6m run, at 450mm per block that's 14 blocks per bay (CEIL(6 ÷ 0.45)), for 98 blocks total. Topping concrete at 50mm across 24m² comes to 1.2m³. At S150's finished 200mm slab depth, supply cost for this floor lands in the R3,360–R12,240 range for ribs and blocks (R140–R510/m² × 24m²), plus roughly R5,040 for topping concrete (R210/m² × 24m²) if self-managed, all 2023/24 pricing, confirm current rates with your supplier.

โš ๏ธ Disclaimer: This calculator provides indicative material quantities for planning purposes only, based on Rhino Slabs' published specification. It does not constitute structural or engineering advice. Slab depth, span, reinforcement and pricing must be confirmed by a structural engineer and your chosen supplier before ordering, cost figures are sourced from 2023/24 published pricing and have not been re-confirmed for 2026. SA Property Tools accepts no liability for decisions made based on this information.

Frequently Asked Questions

A rib and block slab is a suspended-floor construction system using pre-stressed concrete ribs (beams) laid across a span, with hollow concrete infill blocks placed between them, then finished with a thin concrete topping. It's used for basement, first-floor and roof slabs as an alternative to a fully poured concrete slab, and needs no cranes or formwork to install.
Pre-stressed concrete ribs are laid across the span at fixed centres, resting on the supporting walls. Hollow infill blocks are then placed between the ribs, supported by the ribs on either side, filling the floor area. A layer of reinforced concrete topping is poured over the whole surface, tying the ribs, blocks and reinforcing mesh into one structural slab once it cures.
This varies by manufacturer. Rhino Slabs, whose published specification this calculator uses, sells four standard block heights: S120 (120mm, giving a 170mm slab), S150 (150mm, 200mm slab), S205 (205mm, 255mm slab) and S290 (290mm, 340mm slab), all 450mm long by 220mm wide. Other South African suppliers use different block series and dimensions for the same product category, always confirm the exact spec with your chosen supplier before ordering.
Ribs are spaced at fixed centres (590mm for Rhino Slabs' system) across the slab's width, with infill blocks filling the gaps between them along the span length. This calculator works out both from your floor's length and width automatically, since the count depends on the aspect ratio of the floor, not area alone.
For Rhino Slabs' system, the topping is consistently 50mm across all four standard block heights, calculated as the difference between each block's height and its finished slab depth. Always confirm this figure with your own supplier and structural engineer, since topping thickness can vary by system and by engineer's specification.
There is no single published span-per-block-type table, slab depth and span are determined by a structural engineer per SANS 1879 and SANS 10100 based on the actual load and layout. As general context, not a fixed rule: Rhino Slabs' own ribs are rated to span up to 7.8m, and rib and block systems generally achieve clear spans up to around 10m. Always get an engineer's design for your specific project.
Based on the most detailed published breakdown found (dated 2023/24, not yet re-verified for 2026), supply-only materials for ribs and blocks run roughly R140-R510 per square metre depending on block depth, plus around R210 per square metre for topping concrete if self-managed. A fully supplied and installed slab runs approximately R825-R1,080 per square metre. Treat these as a starting guideline only and get a current quote from your supplier, since building material pricing moves and this figure has not been confirmed for 2026.
Rib and block installs faster with no cranes or formwork needed, gives a smooth plastered ceiling underneath with no visible grooves, and reduces propping and labour costs. A fully poured concrete slab, calculated on this site's own Concrete Volume Calculator, can suit different span and load requirements. Get a structural engineer's input on which system fits your specific building before deciding.