⚡ Last Updated: May 2026  ·  SANS 10142 Aligned  ·  Copper PVC 70°C

⚡ Quick fill — tap a common circuit:

🚿 Geyser (3kW)
230V · 5m run · Clipped
🍳 Electric Stove (8kW)
230V · 8m run · Clipped
🔌 Plug Circuit (20A)
230V · 15m run · Conduit
💡 Lighting Circuit (16A)
230V · 20m run · Conduit
❄️ Air Conditioner (5kW)
230V · 12m run · Clipped
⚙️ 3-Phase Motor (11kW)
400V · 10m run · Clipped
Cable Size Calculator — Enter Circuit Details
Check the nameplate on the appliance. 1kW = 1000W
Read from the breaker or DB board label, or use I = P ÷ V
Most homes use 230V single phase
DB board to load point — one way only
Cable in conduit runs hotter — lower current rating applies
Circuit Current
Cable Capacity
Voltage Drop
VD % of Supply
SANS 10142 Limit
Next Size Up

⚠️ For planning purposes only. All electrical work in SA must be carried out by a registered electrician under SANS 10142. A Certificate of Compliance (CoC) is required.

Cable Sizing in South Africa — SANS 10142 Explained

Selecting the correct cable size is one of the most critical steps in any electrical installation. An undersized cable overheats, degrades insulation, creates a fire risk, and will fail a Certificate of Compliance (CoC) inspection. Oversizing wastes money unnecessarily. SANS 10142 — South Africa's wiring code — specifies exactly how cable sizing must be done.

There are two separate tests a cable must pass under SANS 10142, and both must be satisfied independently. This calculator checks both automatically.

The Two SANS 10142 Cable Sizing Checks

Check 1 — Current Carrying Capacity

Every cable has a maximum continuous current it can carry safely without the insulation overheating. For standard copper PVC-insulated cables at 70°C operating temperature, these are the rated values used in South Africa:

Cable Size Clipped Direct (A) In Conduit (A) Volt Drop (mV/A/m) Typical Use
1.5mm²17.5A14A28.0Lighting circuits
2.5mm²25A20A17.0Plugs, geysers (short runs)
4mm²32A26A11.0Geysers, cooktops (short runs)
6mm²41A34A7.1Stoves, pool pumps
10mm²57A46A4.2Large stoves, sub-mains
16mm²75A61A2.7Sub-distribution boards
25mm²100A80A1.7Main DB feeds
35mm²125A100A1.3Main supply cables

Source: MicCom Cables SA / SANS 10142 aligned. Values for copper PVC-insulated cables, conductor operating temperature 70°C.

Check 2 — Voltage Drop

Even if a cable can carry the current safely, it must not drop too much voltage along its length. SANS 10142 sets the maximum voltage drop at 5% of the supply voltage for final circuits:

  • 230V single phase: Maximum 11.5V drop
  • 400V three phase: Maximum 20V drop
Formulas
Current (A) = Power (W) ÷ Voltage (V)   [single phase] Current (A) = Power (W) ÷ (400 × 1.732)   [three phase] Voltage Drop (V) = mV/A/m × Current (A) × Length (m) ÷ 1000 VD % = Voltage Drop (V) ÷ Supply Voltage (V) × 100 SANS 10142 limit = 5% of supply voltage (11.5V / 20V)

Why Installation Method Matters

A cable installed in conduit or enclosed trunking cannot dissipate heat as efficiently as one clipped to a surface or run in open air. This means the same cable has a lower current rating in conduit than when surface-mounted. The SANS 10142 derating for conduit is significant — a 2.5mm² cable drops from 25A (clipped) to 20A (in conduit). Failing to apply this derating results in overloaded cables that overheat and degrade.

Common SA Circuit Examples

These are typical cable sizes used in South African residential installations. Always verify with a registered electrician, as actual installations depend on run length, grouping, and ambient temperature.

  • Lighting circuits: 1.5mm² (up to 20m runs), 2.5mm² for longer runs
  • 15A plug circuits: 2.5mm² (short runs), 4mm² (over 25m)
  • Geyser 3kW: 2.5mm² (under 15m), 4mm² (15–30m)
  • Electric stove 6–9kW: 6mm² minimum, 10mm² for longer runs
  • Air conditioner 3–5kW: 2.5mm² (short runs), 4mm² (over 15m)
  • DB board sub-mains: 10mm²–25mm² depending on total load
  • Inverter / solar feed: 10mm²–25mm² depending on inverter size and run length

Frequently Asked Questions

What cable size do I need for a 3kW geyser in South Africa?
A 3kW geyser draws approximately 13A on a 230V single-phase supply. A 2.5mm² cable handles this for short runs, but for runs over 20m a 4mm² cable may be needed to stay within the SANS 10142 5% voltage drop limit. Geysers require a dedicated circuit with a 20A double-pole breaker and an earth leakage device.
What cable size do I need for a stove or oven?
A typical 6–9kW electric stove draws 26–39A on a 230V supply, requiring a minimum 6mm² cable for short runs. For longer runs, 10mm² may be needed for voltage drop compliance. Always check the stove nameplate for the rated current and consult a registered electrician for the correct breaker size.
How do I calculate cable size in South Africa?
Cable sizing involves two checks under SANS 10142: (1) Current carrying capacity — select a cable rated above your load current. (2) Voltage drop — calculate VD = mV/A/m × Amps × Length ÷ 1000. The result must be under 11.5V for 230V circuits or 20V for 400V circuits. This calculator does both checks automatically and flags when a larger cable is needed for voltage drop reasons even if current capacity is adequate.
What is SANS 10142 and why does it matter?
SANS 10142 is South Africa's national standard for the wiring of premises. It is the code registered electricians must follow for all new installations and alterations. It covers cable sizing, voltage drop limits, breaker sizing, earthing, and installation methods. Non-compliant wiring will fail a Certificate of Compliance inspection — which is mandatory when selling a property.
What is the maximum voltage drop allowed in South Africa?
SANS 10142 sets the maximum voltage drop at 5% of the nominal supply voltage for final circuits. That is 11.5V on a 230V single-phase supply and 20V on a 400V three-phase supply. Exceeding this causes appliances to underperform, motors to overheat, and trips on sensitive equipment. It will also fail a CoC inspection.
Can I install electrical cable myself in South Africa?
No. Under South Africa's Electrical Installation Regulations 2009, all electrical work must be carried out or directly supervised by a registered person — a wireman's licence holder registered with the Department of Employment and Labour. DIY electrical work is illegal, will not receive a CoC, and creates serious fire and safety risks. Use this calculator for planning only, then instruct a registered electrician.

🔧 Related Artisan Tools

All Trades & Artisan Tools Building Cost Calculator — Estimate Construction Costs by Province Property ROI Calculator — Is Your Investment Worth It?